The Raynham Board of Sewer Commissioners begins their monthly meeting with solemn reflections on the anniversary of 9/11, sharing personal memories of that tragic day before tackling the town's infrastructure challenges.
• Ongoing issues at the Market Basket Pumping Station where soap suds are causing pumps to fail and require emergency maintenance
• Successful implementation of a new experimental pump at White Street station working "flawlessly"
• Completion of sewer billing for January-June 2025 after resolving conversion issues with the VADAR system
• Updates on the 44 pump control project requiring additional equipment for better bypass capabilities
• Progress on local road improvements including Mill Street and Elm Street East projects
• Temporary repairs to the South Street East Old Colony Bridge allowing full traffic flow
• Approval of a $7,264.12 change order for electronic controller and wiring improvements at a pumping station